13th May 2013 Week One

Strip out and installation of beautiful Moduplay structure!

20th May 2013 Week Two

Site Preparation. Installation of sandstone, logs and a few other items.

And it rained - but no delaying Andrew, Lloyd and Ethan!

   

27th May 2013 Week Three

Installation of special things!

   

3rd June 2013 Week Four

Installation of timber platform and rubber surfacing

11thJune 2013 Week Five

Rain, rain go away! Slight delay for installation of the surfacing - we did manage to have the Working Bee! What a difference plants make!

 

Paul's red socks helped him work harder!

"Before" the planting!     

Russell from Forpark digs, digs, and digs with determination!

Mick (far right) also did a lot of digging!

 

Thank you!!!!

  • Fiona T
  • Mick
  • Katrina L
  • Russell T
  • Sophie T
  • Beverley B
  • Sarah B
  • Vicki M
  • Kate M
  • Christine E
  • Paul L
  • Kay L
- the local fauna thanks us too!
    
 

17th June 2013 Week Six Installation of 'Polysoft'

'Rain, rain, go away!!'
 

24th June 2013 Week Seven Installation of synthetic grass and sandpit restoration.

 